Present Status
- Survey License obtained on 2078/11/18.
- Connection Agreement signed on 2079/02/18.
- Supplementary-Initial Environmental Examination (S-IEE) approved on 2079/10/18.
- Generation License obtained on 2080/01/20.
- PPA with NEA concluded on 2080/08/05.
- Transmission Line Survey License obtained on 2081/01/03.
- Detailed investigations: ERT/Drilling completed for major project locations.
- Updated Feasibility Study Report: Completed
- Design Review from NTNU Norway: Completed
- Detailed Engineering: Ongoing
- Infrastructure Development Contractor: Mobilized
- Construction Supervision Team: Mobilized
- Land Acquisition: Private land procurement and lease completed
- Project Access Road: Under Construction
- Camp Houses: Under construction
- Army Camp: Under construction
- Construction Power: Under Construction
- Due Diligence Audit: Completed
- Lead Bank: Finalized as Sanima Bank Limited